Evictly

Razavi Khosravani Nejad v Rad

Landlord wins · Richmond Hill · 2025-10-03

Adjudicator
Harry Cho
Dispute
Non-payment of Rent, Utilities
Landlord
H.R.K.N.
Tenant
E.R.

What happened

The Landlord applied for rent arrears and unpaid utility costs. An order was issued on August 28, 2025, in favor of the Landlord. The Tenant requested a review of that order, claiming the findings of fact regarding rent and electricity arrears were incorrect. The Board conducted a preliminary review to determine if a serious error existed in the original decision.

The ruling

The Tenant's request for a review of the order issued on August 28, 2025, is denied. The original order, which found the Tenant liable for rent arrears and $799.48 in electricity costs, is confirmed and remains unchanged.