D Cubed Enterprises Inc. v Thompson
Split/Other wins · Welland · 2025-04-17
- Adjudicator
- Sheena Brar
- Dispute
- Non-payment of Rent, Persistent Late Payment
- Notice
- Non-payment of rent (N4), Persistent late payment (N8)
- Amount
- <$5K
- Landlord
- D Cubed Enterprises Inc.
- Tenant
- D.T.
- Landlord rep
- E. Grigorieva
What happened
The Landlord applied to terminate the tenancy based on rent arrears and persistent late payment. During the hearing, both parties reached a consent agreement regarding the payment of outstanding arrears and the timeliness of future rent payments.
The ruling
The parties entered into a consent order where the Tenant agreed to pay $283.46 by April 30, 2025. Additionally, the Tenant is required to pay rent on time for the next twelve months. Failure to comply with these terms allows the Landlord to seek an eviction order without further notice to the Tenant.